Throgs Neck Bridge

Renovation of the Queens Approach to the Throgs Neck Bridge

The Queens approach of the 49-year-old bridge was replaced under a $96.7 million contract. Main features of project included replacement of the entire concrete roadway deck at the Queens side of the span, rehabilitation of abutment and concrete retaining walls, and painting of structural steel including the Cross Island Parkway on- and off-ramps. More than 140,000 square feet of the roadway deck on 11 spans of the bridge in Queens was replaced.

E.E. Cruz Corporation

New York, New York